Step 1 - Préparation des accessoires

Matériel nécessaire : soudeuse, cliveuse, pince à dénuder, lingettes non pelucheuses, alcool isopropylique et protections d'épissure thermorétractables (smooves).




Step 2 - Dénudage et nettoyage de la fibre

Dénuder sur 3/4 cm, nettoyer la fibre dénudée avec l'alcool isopropylique avant de cliver.

NB : ne plus toucher avec les doigts la fibre une fois nettoyée.


Step 3 - Clivage de la fibre

Positionner la fibre dans la rainure adaptée du guide fibre (250 ou 900 µm), la gaine 250 ou 900 µm à la graduation 10 en faisant attention que la partie dénuée prenne bien appui sur les 2 patins.



Step 4 - Positioning the fibre in the welder

Position the fibre in the fusion splicer by placing its end between the alignment of the electrodes and the edge of the V-slot, close the valve retaining the fibre.

NB: Be careful not to hit the end of the fibre as this may alter the quality of the cleavage.

You must now repeat these operations for the second fibre.


Step 5 - Choosing the programs of the welder machine

Use the welding program adapted to the type of fibre to be welded, as well as the furnace program adapted to the type of smoove used.

Example: Single mode MS, multi-mode MM and single mode BIF G657.

Step 6 - Welding process

Close the cover to initiate the welding process (the auto start function must be activated otherwise press the green arrow on the keyboard).


Step 7 - Welding evaluation

Three evaluation criteria should be observed: the image quality of the welded fibres (good alignment of the cores, absence of dust or air bubbles, etc.), the estimated loss given by the fusion splicer and the resistance of the fibre to the tensile test (not to be disabled).


Step 8 - Positioning the smoove and shrinkage

Before opening the cover, bring the smoove as close as possible to the fusion splicer, center it at the weld, making sure that the shrinkage will be on the fibre protection sheaths and not on the bare fibre. Position the smoove in the center of the furnace. The furnace is activated automatically if this function has been previously selected in the machine parameters, otherwise press the yellow resistance on the keyboard.


Step 9 - Positioning the smoove on a cassette for winding

After shrinking, position the smoove on the cooling plate before welding other fibres. Then place the smooves in the cassette and wind the fibres.